Math, asked by wwwsarthak025, 5 days ago

a b and c can do a work in 12 15 and 20 days respectively they started working together but after 4 days a left in how many days will b and c complete the work.One who answer correctly I mark he/she at brainliest​

Answers

Answered by ayushajaythakare1020
0

Answer:

Work is done by A in one day =

15

1

By B=

12

1

C=

20

1

Together in 1 Day =

15

1

+

12

1

+

20

1

=

60

4+5+3

=

60

12

=

5

1

2 days work =

5

2

Remaining work = 1−

5

2

=

5

3

one day work of A,B ⇒A+B=

15

1

+

12

1

=

60

4+5

=

60

9

=

20

3

(A+B) work for t days =

20

3

t=

5

3

t=4 days

A and B will complete the work in 4 days