A, b and c can do a work separately in 16, 32 and 48 days respectively. they started the work together but b leaving off 8 days and c six days before the completion of the work. in what time is the work finished?
Answers
Answered by
18
A B C
Done: 16 32 48
Can : x x-8 x-6
Work = done/can
X/16+(x-8)/32+(x-6)/48=1
Lcm is 96
6x+3x-24+2x-12/96=1
So x=12days... So work will be completed after 12 days
Done: 16 32 48
Can : x x-8 x-6
Work = done/can
X/16+(x-8)/32+(x-6)/48=1
Lcm is 96
6x+3x-24+2x-12/96=1
So x=12days... So work will be completed after 12 days
Answered by
12
Answer: The work is finished in 12 days.
Step-by-step explanation:
Let the work done by A in x days.
Let the work done by B in x-8 days.
Let the work done by C in x-6 days.
Since we have given that
Number of days in which A can finish his work = 16 days
Number of days in which B can finish his work = 32 days
Number of days in which C can finish his work = 48 days
According to question,
Hence, the work is finished in 12 days.