A,B and C can reap a field in 63/4 days; B,C ,and D in 14 days; C,D and A in 18 days; D,A and B in 21 days. In what time can A,B,C and D together reap it?
Answers
Given:
Time taken to reap the field are as follows:
A, B & C in days
B, C & D in 14 days
C, D & A in 18 days
D, A & B in 21 days
To find:
Time taken by A, B, C & D together to reap the field
Solution:
The amount of work done in reaping the field 1 day is:
A + B + C →
B + C + D →
C + D + A →
D + A + B →
Now,
The amount of work done by A, B, C & D together in 1 day will be:
[A + B + C] + [B + C + D] + [C + D + A] + [D + A + B] =
⇒ [3A + 3B + 3C + 3D] =
⇒ 3 [A + B + C + D] =
⇒ [A + B + C + D] = ×
⇒ [A + B + C + D] =
⇒ [A + B + C + D] =
Thus,
---------------------------------------------------------------------------------------
Also View:
A man takes 10 days to finish a job were as a women takes 6 days to finish a same job . together they worked for 3 days and then the women left. in how many days will the man complete the remaining work?
https://brainly.in/question/15033170
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work
https://brainly.in/question/8587762
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722