Math, asked by 4mahesh8, 8 months ago


A, B and c
together can complete a piece
in 10 days. Work can be also completed when
A and B together work for 12 days and
c work for 7.5 days. find the time taken by C
alone to do that work?​

Answers

Answered by SATISH444
1

Answer:

7.5 days

Step-by-step explanation:

It's given in question itself.