Math, asked by vvv4, 3 months ago

A B C can a piece of work in 3,5,6 days . How many time they will take to complete work together. If they earn rupee 1050 how they will divide the money
please send a easy way I send you answer
A= 500
B=300
C=250​

Answers

Answered by crackmehkma7172
0

Answer:

A can complete the work in 4 days

B can complete the work in 5 days

C can complete the work in 7 days.

Total work 4×5×7=140 units

A’s efficiency is 140/4 = 35

B’s efficiency is 140/5=28

C’s efficiency is 140/7=20

A will get 415 × 35/83= Rs.175/-

B will get 415 × 28/83= Rs140/-

C will get 415 × 20/83= Rs.100/-

Similar questions