Math, asked by viniee7661, 1 year ago

A,B,C can do a work in 12,24,8 days they all work for 1 day. Then C leaves the group. In how many days will A and B complete the work

Answers

Answered by tinapreetika204
0

Answer:

Step-by-step explanation: