Math, asked by Nimish1734, 1 year ago

A,b,c can do a work in 20 days,40 days and 60 days respectively.if they work together jow long will it take to complete the work

Answers

Answered by aknowshadclix
0

A. 12 days

B. 15 days

C. 16 day