A,B,C can do apeace of work in 15,12,20 respectively. They started the work together , but C left after 2 days , In how many days the remaining work be completed by A and B.
Answers
Answered by
2
Answer:
Step-by-step explanation:
Attachments:
Answered by
2
Answer:
4 days
Step-by-step explanation:
See the attached image. Hope it helps you.
Attachments: