A,B,C together finish a work in 4 days. If alone can finish the same work in 8 days and B in 12 days find how long will C take to finish
Answers
Answered by
9
A's 1 day of work = 1/8
B's 1 day of work = 1/12
(A+B+C)'s 1 day of work = 1/4
C's 1 day of work = 1/4 -(1/8+1/12)
= 1/24
Hence, C can finish the same work in 24 days.