Math, asked by sharmilrana3302, 1 year ago

A,band c together can do a piece f work in 40 days .After working with a,b and c for 16 days, a leaves and then b and c complete the remaining work in 40 days more.A alone could do the work in

Answers

Answered by aashi8296
0

A,B,C can together do a work in 40 days. After working with B and C, A leaves after 16 days and the remaining work is completed by B and C in 40 days. In How many days A can work alone to finish the work?

Answer:-

Work done by A,B,C in 1 day

=

1

40

Work done by A,B,C in 16 days

=

16

40

=

2

5

Remaining work

=

1

2

5

=

3

5

.

This remaining work

3

5

is completed by B and C in 40 days.

Therefore work done by B and C in 1 day

=

(

3

5

)

40

=

3

200

Work done by A in 1 day

=

1

40

3

200

=

1

100

Therefore A alone can finish the work in 100 days.

Similar questions