Math, asked by jameelkhan19573, 9 months ago


A bridge can be constructed by 1500 workers in 60 days. How many more such peopleshould be employed to complete work in 40
days.​

Answers

Answered by babitajain0251
2

Answer:

Step-by-step explanation: by direct and inverse variation method :

let the no. be men be x

its a case of inverse proportion

1500 x 60 = x × 40

90000= 40x

90000/40 = x

2250 = x