A building contractor undertook to finish a certain work in 162 days and employed 150 men. After 72 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work finish in time? ​

Answers

Answered by shindesarthak796
2

Step-by-step explanation:

a) 80

b) 75

c) 90

d) 70

e) 65

Correct answer is option 'C'.