A building contractor undertook to finish a certain work in 162 days and employed 150 men. After 72 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work finish in time?
Answers
Answered by
2
Step-by-step explanation:
a) 80
b) 75
c) 90
d) 70
e) 65
Correct answer is option 'C'.