a can build a wall in 12 days, b can do the same in 16 days and c can do in 24 days. totally 6 walls are to be built. 'a' does the work for first 16 days and 'b' continues the work for the next 12 days. how many days should c work?
Answers
Answered by
2
hi I am a a a a a a a a a a a a a a a a a a a a a a a a a
Answered by
4
94 days is the number of days to complete the work by C.
Given:
A can build a wall in 12 days
B can build a wall in 16 days
C can build a wall in 24 days
To find:
The time taken by C to complete the left over work
Solution:
6 walls are built in total
A does the work for 16 days, so A completes one wall in 12 days.
In balance 4 days A completes, of the second wall.
Work done by A of second wall
B works for next 12 days of the wall
Total work done by A and B
Remaining walls
C can build a wall in 24 days
Hence it takes days to build 3 walls by C
To build of the wall
To build of the wall
Total work done by C
Therefore, the total work done by C is 94 days.
Similar questions