Math, asked by brijeshmishra27, 6 hours ago

A can complete 40% of a work in 16 days . B is 25% less efficient than C . C takes 16 days less than A to complete the work. In how many days A and B together can complete 84.375% of work together?

Answers

Answered by RvChaudharY50
0

Given :- A can complete 40% of a work in 16 days . B is 25% less efficient than C . C takes 16 days less than A to complete the work. In how many days A and B together can complete 84.375% of work together ?

Solution :-

→ A can complete 40% of a work in = 16 days .

so,

→ A can complete 100% of a work in = (16/40) * 100 = 40 days .

now,

→ Time taken by C to complete the work = 16 days less than A = 40 - 16 = 24 days .

then,

→ Time taken by B to complete the work = (24 * 100)/75 = 32 days .

now,

→ LCM of (40 and 32) = 160 units = Let total work .

so,

→ Efficiency of A = Total work / time taken = 160/40 = 4 units / day

→ Efficiency of B = Total work / time taken = 120/32 = 5 units / day

then,

→ Efficiency of (A + B) = 4 + 5 = 9 units / day.

therefore,

→ Time taken by A and B to complete 84.375% of work together = (160 * 84.375/100) / 9 = 135 / 9 = 15 days (Ans.)

Learn more :-

Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...

https://brainly.in/question/21025557

Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...

https://brainly.in/question/14687371

Answered by amitnrw
2

Given :  A can complete 40% of a work in 16 days .

B is 25% less efficient than C .

C takes 16 days less than A to complete the work.

To Find : In how many days A and B together can complete 84.375% of work together?

Solution:

A can complete 40% of a work in 16 days .

=> 100 % can be done in  16 * 100 / 40  = 40 Days

C takes 16 days less than A to complete the work

=> C can complete in   40 - 16  = 24 Days

C' 1 day work  = 1/24

B is 25% less efficient than C

=> B's 1 day work  =  C's 1 day work - 25 % less

= 1/24   - (25/100)(1/24)

=   1/32

A & B  together 1 day work  = 1/40 + 1/32

= ( 4 + 5)/160

= 9/160

Hence 100 % work will be completed in  160/9  days

=> 84.375% of work will be done  =  (84.375 / 100 ) (160/9)

=  9,375 * 16 / 10

= 150 /10

= 15 Days

A and B together can complete 84.375% of work together in 15 Days

Learn More:

14 men can dig a wall in 9 days how many men can dig in 21 days

brainly.in/question/7373555

A and B can do a piece of work in 12 days; A,B and C all working ...

brainly.in/question/7839397?source=aid17352661

A takes 6 days and B takes 4 days to complete amasonry work when ...

brainly.in/question/14669213

Similar questions