A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in:
Answers
The number of days B take alone to complete the remaining work is 32 days .
Step-by-step explanation:
Given as :
A can complete a certain piece of work in 40 days
B is 25% more efficient than A
C is 28% more efficient than B
The number of days all three works together = 5 days
Let The number of days B take alone to complete the work = d days
According to question
Ratio of efficiency by A and B = 125 : 100
i.e Ratio of efficiency taken by A and B = 5 : 4
Then ,
Ratio of efficiency taken by A and B = Ratio of days taken by A and B
i.e 5 : 4 = 40 : d
Or, =
By cross multiplication
or, 5 × d = 4 × 40
Or, d =
∴ d = 32
So, The number of days B take alone to complete the work = d = 32 days
Similarly
Ratio of efficiency taken by C and B = 128 : 100
i.e Ratio of efficiency taken by C and B = 32 : 25
Ratio of efficiency taken by C and B = Ratio of days taken by C and B
Let number of days C take alone = D days
i.e 32 : 25 = D : 32
Or, =
By cross multiplication
or, 32 × 32 = D × 25
Or, D =
∴ D = 40
So, The number of days C take alone to complete the work = D = 40 days
Hence, The number of days B take alone to complete the remaining work is 32 days . Answer
A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by b alone,in: 32 days
Stepwise explanation is given below:
It is given that the-
- A can complete a certain piece of work in 40 days.
B is 25% more efficient than A
C is 28% more efficient than B
- The number of days all three works together = 5 days.
- The number of days B take alone to complete the work = d days
- Acc. to the question
Ratio of efficiency by A and B = 125 : 100
i.e Ratio of efficiency taken by A and B = 5 : 4
- Ratio of efficiency taken by A and B = Ratio of days taken by A and B
i.e 5 : 4 = 40 : d
Or, (5/4) = (40/d)
- By cross multiplication
5 × d = 4 × 40
5d = 4 × 40
d= (4 × 40)/5
d= 32
- So, The number of days B take alone to complete the work = d = 32 days.