Math, asked by mukulparmar4687, 10 months ago

A can complete a job in 6 days and b can complete the same job in 4 days . If both work together

Answers

Answered by anksatyajeetow2grb
0

Answer: 12/5 or 2.4 days

Step-by-step explanation:

Work done by A in 1 day = 1/6

Work done by B in 1 day = 1/4

Work done by A and B together in 1 day =

1/6+1/4

= (2+3)/12

= 5/12

If 5/12 work is done by A and B together in 1 day, then 1 work will be done in 12/5 days.