A can complete a piece of work in 10 days, b in 15 days and c in 20 days. A and c worked together for two days and then a was replaced by b. In how many days, altogether, was the work completed ?
Answers
In 1 day A completes = 1/10 part of the work
In 1 day B completes = 1/15 part of the work
In 1 day C completes = 1/20 part of the work
In 1 day A and C together complete = (1/10) + (1/20)
= (2+1)/20
= 3/20 part of the work
∴ In 2 days A and C together complete = 2× 3/20
= 3/10 part of the work
∴ The amount of work left = 1-3/10
= 10-3/10
= 7/10 part of the work
In 1 day B and C together complete = (1/15)+(1/20)
= (4+3)/60
= 7/60 part of the work
7/60 part of the work is done within 1 day
∴ 1 part of the work is done in (60/7) days
∴ 7/10 part of the work is completed in = (60/7)×(7/10)
= 6 days.
∴ B and C will together complete the remaining work in 6 days.
In 1 day A,B,C together do =(1/10)+(1/15)+(1/20)
= (6+4+3)/60
= 13/60 part of the work
13/60 part of the work is completed in 1 day
∴ 1 part of the work is completed in = (60/13)
= 4+(8/13) days
∴ They altogether complete the work in 4 whole of 8/13 days
If according to the question A and C worked together for 2 days AND then B replaced A then, the work would be completed within (6+2)
= 8 days
So, the answer is 8 days.
Answer:
The answer is 8 days.
Step-by-step explanation:
- A completes work in 10 days.
- B completes work in 15 days.
- C completes work in 20 days.
Work can be calculated by finding the product of time and efficiency.
The formula used to calculate for work is
Work= Time x Efficiency
1. Firstly we will find the LCM (Lowest Common Multiple) of A,B,C.
2. LCM of 10,15 and 20 is 60.
3. The efficiency of A,B and C is:
- The efficiency of A will be 60/10 = 6
- The efficiency of B will be 60/15 = 4
- The efficiency of C will be 60/20 = 3
4. A and C work for two days
Therefore, they completed
⇒ (6+3) x 2 days = 18 units.
Therefore, the work left will be
⇒ 60 - 18 = 42 units.
5. Now A is replaced by B, (B+C) one day
⇒ 4+3 = 7 unit
6. Therefore, the remaining work will be completed in
⇒ 42/7 = 6 days ..........(i)
Therefore, the total work completed will be 6 (i) +2 (as per the question) = 8 days.
Thus, altogether the work was completed in 8 days.