A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and the B
completed the remaining work along with C in 18 days. In how many days can C complete
the work?
Answers
Answered by
9
A completes 120 of the job per day.
B completes 130 of the job per day.
C completes 1c of the job per day.
In 4 days, A completes 4 days ×120 jobday=15 job; 45 job remaining.
In 18 days, B completes 18 days ×130 jobday=35 job; 15 job remaining.
In 18 days, C completes 18 days ×1c jobday=18c job =15 job.
c=90C can do the job alone in 90 days
Answered by
1
Step-by-step explanation:
A+B's 20 day's work=
30
1
×20=
3
2
Remaining work=1−
3
2
=
3
3−2
=
3
1
Now,
3
1
rd
work is done by A in 20 days.
∴ The whole work will be done by A in 20×3=60 days.
Similar questions
Geography,
1 month ago
Math,
2 months ago
Math,
2 months ago
Science,
8 months ago
India Languages,
8 months ago