A can complete a work in 20 days and B in 30 days.A worked alone for 4 days and then B completed the remaining work along with C in 18 days.In how many days can C working alone complete the work?
Answers
Answered by
0
ans is 20-30+4-18 now slve it and find
RebelRavish6:
Oo u r right now
Answered by
3
I found this ..Hope it helps.