A can complete a work in 45 days and B can do it in 40 days. They work together for
9 days and then A leaves. In how many days will B finish the remaining work?
Answers
Answered by
0
Answer:
A's 1 days' work =451,B's 1 days' work =401
Suppose A left the work after x days of the start of the work. Then,
Work done by A in x days =45x
Work done by B in (x+23) days =40(x+23)
Given, 45x+40(x+23)=1⇒360(8x+9x+207)=1
⇒17x=360−207=153⇒x=17153=9 Days