A can do 75% of a job in 9 days and b can do half of the job in 8 days. if they work on it together, then in how many days can they do half of the job? options:

Answers

Answered by Thatsomeone
4
GIVEN-

A can complete 75%job in 9 days

B can complete 50% job in 8 days

TO FIND-

If they work together then the number of days to complete the job

SOLUTION

A can complete the whole job in 100×9/75=12 days

B can complete the whole job in 100×8/50=16 days

A can do 1/12 part of job in one day

B can do 1/16 part of job in one day

The part of job done by A & B in one day =1/12+1/16

=8+6/96

=14/96

=7/48

so the no. days are 48/7