A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in
Answers
Answered by
25
Given
Let the A's One day work be 1 / 16
Let the B's One day work be 1/ 12
Let A,B and C's One day work be 1/ 6
To Find
how much time will be taken for C alone.
Solution
C's One day work will be the subtraction of A and B's work from the total ,
Here L.C.M = 48 and therefore ,
So , C person can complete the work within 48 days.
Answered by
38
Answer:
Given :-
- A can do a job in 16 days and B can do the same job in 12 days.
- With the help of C, they finish the job in 6 days only.
To Find :-
- How many days need to finish the job by C alone.
Solution :-
Given :
A can do a job in 16 days.
Let,
Again,
B can do the same job in 12 days.
Let,
According to the question :
A, B and C can do the same job in 6 days.
So,
By putting those values we get,
C can finish the job alone in 48 days .
▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃
Similar questions