Math, asked by ashishkumar8430, 3 days ago

A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in​

Answers

Answered by MysticPetals
25

Given

Let the A's One day work be 1 / 16

Let the B's One day work be 1/ 12

Let A,B and C's One day work be 1/ 6

To Find

how much time will be taken for C alone.

Solution

C's One day work will be the subtraction of A and B's work from the total ,

 \longrightarrow \:  \dfrac{1}{6}  - ( \frac{1}{12} +  \frac{1}{16} )

 \implies \:  \dfrac{1}{6}  -  \dfrac{1}{16 }  -  \dfrac{1}{12}

Here L.C.M = 48 and therefore ,

 \implies \: \:  \dfrac{8 - 3 - 4}{48}

 \implies \:  \dfrac{1}{48}

So , C person can complete the work within 48 days.

Answered by StarFighter
38

Answer:

Given :-

  • A can do a job in 16 days and B can do the same job in 12 days.
  • With the help of C, they finish the job in 6 days only.

To Find :-

  • How many days need to finish the job by C alone.

Solution :-

Given :

\bigstar A can do a job in 16 days.

Let,

\mapsto \bf A\: can\: do\: a\: job\: in\: 1\: day = \dfrac{1}{16}\\

Again,

\bigstar B can do the same job in 12 days.

Let,

\mapsto \bf B\: can\: do\: the\: job\: in\: 1\: day =\: \dfrac{1}{12}\\

According to the question :

\bigstar A, B and C can do the same job in 6 days.

So,

\implies \sf\bold{\purple{A + B + C =\: \dfrac{1}{6}}}\\

By putting those values we get,

\implies \sf \dfrac{1}{16} + \dfrac{1}{12} + C =\: \dfrac{1}{6}\\

\implies \sf \dfrac{3 + 4}{48} + C =\: \dfrac{1}{6}\\

\implies \sf \dfrac{7}{48} + C =\: \dfrac{1}{6}\\

\implies \sf C =\: \dfrac{1}{6} - \dfrac{7}{48}\\

\implies \sf C =\: \dfrac{8 - 7}{48}

\implies \sf C =\: \dfrac{1}{48}

\implies \sf\bold{\red{C =\: 48}}\\

\therefore C can finish the job alone in 48 days .

\\

▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃

Similar questions