A Can do a of work 10 days and B in 15 days .How long will take together to finish it

Answers

Answered by aditya1139
2
a' 1 day work = 1/10
b' 1 day work =1/ 15
=1/10+1/15
=5/30
= taken time by both a and b finish the work
= 6 days
Answered by abhi123hero
0
6 is the correct answer