a can do a piece of work in 10 days and b can do it in 12 days. if they work alternativly
Answers
Answered by
1
A's one day work =1/10.
B's one day work =1/12.
they work alternatively.....
(A+B)'s one day work =1/10+1/12
6+5/60
11/60.
please mark as the BRAINLIEST.
B's one day work =1/12.
they work alternatively.....
(A+B)'s one day work =1/10+1/12
6+5/60
11/60.
please mark as the BRAINLIEST.