A can do a piece of work in 10 days and B can do the same work in 15 days. they work together for 3 days and then B leaves.In how many days will A alone can complete the remaining work.​

Answers

Answered by bihadunethmika1234
1

Answer:

a work alone

7.5 days

Step-by-step explanation: