Math, asked by shallumittal7171, 1 year ago

A can do a piece of work in 10 days, b in 15 days. they work together for 5 days, the rest of the work is finished by c in two more days. if they get rs. 3000 as wages for the whole work, what are the daily wages of a, b and c respectively (in rs):

Answers

Answered by DayWalker
0
800&700 respectively.
Answered by divakarkumar424
0

Answer:

A's 5 days work = 50%  

B's 5 days work = 33.33%  

C's 2 days work = 16.66%     [100- (50+33.33)]  

Ratio of contribution of work of A, B and C = 50 : 3313 : 1623 = 3 : 2 : 1    

A's total share = Rs. 1500  

B's total share = Rs. 1000  

C's total share = Rs. 500  

 

A's one day's earning = Rs.300  

B's one day's earning = Rs.200  

C's one day's earning = Rs.250

Step-by-step explanation: