A can do a piece of work in 10days and b in 20days.They begin together but a leaves 2 days before the completion of the work. The whole work will be done in how many days?
Answers
Answered by
43
The whole work will be done in 8 days.
Step-by-step explanation:
Let the work will be done in x days.
1 day work of A = 1/ 10
1 day work of B = 1/20
x - 2 / 10 + x / 20 = 1
2x - 4 + x / 20 = 1
3x - 4 = 20
3x = 24
x = 8 days
Hence the whole work will be done in 8 days.
Also learn more
A can do a piece of work in 20 days and b in 15 days. with help of c, they finish the work in 5 days. in how many days c alone can do the same work?