A can do a piece of work in 12 days and b can do it in 20 days. a worked for 9days and leaves the work
Answers
Answered by
1
let work be 120 ( lcm of 12 and 20 )
A needs 12 days
so A doing 10 work per day
B needs 20 days
so A doing 6 work per day
first A does work for 9 days
therefore 9×10 =90 work accomplish
now A leaves , B joins , 30 work remains
B doing 6 work per day so
for 30 work B takes 30/6 = 5 days
so remaining work B completes in 5 days
or total 9 + 5 =14 days requires
A needs 12 days
so A doing 10 work per day
B needs 20 days
so A doing 6 work per day
first A does work for 9 days
therefore 9×10 =90 work accomplish
now A leaves , B joins , 30 work remains
B doing 6 work per day so
for 30 work B takes 30/6 = 5 days
so remaining work B completes in 5 days
or total 9 + 5 =14 days requires