A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If they comolete work was finished in 8 days. In how many days B can alone do the work
Answers
Answered by
0
Answer:
STANDARD PLEASE
Step-by-step explanation:
Answered by
0
Step-by-step explanation:
In 8- days A- alone can complete = 8/12= 2/3- part of the work. The remaining (1–⅔)= ⅓- part of the work was completed by B- alone in (8–2)= 6- days. Therefore B- alone can complete the work in= 6÷⅓= 18- days.
plz mark me the brainliest...
Similar questions