Math, asked by rajnaskar999, 1 year ago

A can do a piece of work in 14 days which B alone can do in 21 days. They
begin together but 3 days before the completion of the work, A leaves off. The
total number of days for the work to be completed is

Answers

Answered by rhe
4

Answer:

A=1/14

B=1/21

1/14+1/21=(3+2)/42

Total work 42 days

A's one day work 3

B's one day work 2

Last 3 days done by only B so 2*3=6 work

Remaining work 42-6=36 work completed by A and B

A+B one day work 5

Remaining 36 work done by A and B

36/5=7.2

Total time=7.2+3=10.2 days