A can do a piece of work in 14 dys and b in 21 days a leaves 3 days before the completion of the work
Answers
Answered by
1
Step-by-step explanation:
They will complete the work in 8.5 days.
Attachments:
Answered by
10
If A can do the work in 14 days, his work per day
If B can do the work in 21days, his work per day
If A & B work together, work per day
Hence, work will be completed, If A & B work together
If A leaves 3 days before completion of work, hence they worked together for 5 days.
Hence completed work in 5 days
Remaining work
Hence, Number of days required for B to complete
hope it helps ☺️
Similar questions