Math, asked by rilemka8951, 11 months ago

A can do a piece of work in 14 dys and b in 21 days a leaves 3 days before the completion of the work

Answers

Answered by Anonymous
1

Step-by-step explanation:

They will complete the work in 8.5 days.

Attachments:
Answered by Anonymous
10

\huge\bigstar\mathfrak\blue{\underline{\underline{SOLUTION:}}}

If A can do the work in 14 days, his work per day

 \frac{1}{14}

If B can do the work in 21days, his work per day

  \frac{1}{21}

If A & B work together, work per day

 =  > ( \frac{1}{14} ) + ( \frac{1}{21} ) \\  \\  =  >  \frac{5}{42}

Hence, work will be completed, If A & B work together

 =  >  \frac{42}{5}  =( 8  + \frac{2}{5} )days

If A leaves 3 days before completion of work, hence they worked together for 5 days.

Hence completed work in 5 days

 =  > 5 \times ( \frac{5}{42} ) =  \frac{25}{42}

Remaining work

 =  > 1 - ( \frac{25}{42} ) \\  \\  =  >  (\frac{42 - 25}{42} ) \\  \\  =  >  \frac{17}{42}

Hence, Number of days required for B to complete

 =  >  \frac{ \frac{ \frac{17}{42} }{1} }{21}  =   \frac{17}{42}  \times 21 \\  \\  =  >  \frac{17}{2}  = 8.5 \: days

hope it helps ☺️

Similar questions