Math, asked by aditi11choudhary22, 9 months ago

A can do a piece of work in 15 days and B in 20 days. With the help of C, the work gets
finished in 5 days. How long will C take to finish the work alone?​

Answers

Answered by BishalSinghMehra
0

Answer:

C can complete the work in 12 days.

Answered by rick3733
0

Step-by-step explanation:

C can do the work in twelve (12) days