a can do a piece of work in 20 days and b can do a piece of work in 30 days. they work together for few days and then b goes away. if a finishes the remaining work in 4 days. how long do they work together
Answers
Answered by
1
Answer:
ok ok
Step-by-step explanation:
good night friends
Answered by
0
Answer:
ANSWER
A's 1 day's work =
25
1
Similarly, B's 1 day's work =
20
1
A's and B's together 1 day's work
25
1
+
20
1
=
100
4
+
100
5
=
100
4+5
=
100
9
Their 5 day's work together = 5 x 1 day's work
1−
100
45
=
100
100
−
100
45
=
100
100−45
=
100
55
Now, this remaining work is done by B.
Let B takes x days to complete it.
20
1
×x=
100
55
⇒x=
100
55
×20
⇒x=
5
55
⇒x=11
Hence, B will finish the remaining work in 11 days.