A can do a piece of work in 20 days and B in 30 days.they began to work together but A left after some days B finished the remaining work in 10 days after how many days did A leave
Answers
Answered by
2
Answer:
Step-by-step explanation:
A can do a work in 20 days.
A's 1 day work =1/20
B cn do a work in 30 days.
B's 1 day work=1/30
(A+B)'s 1 day work=1/20+1/30
=(30+20)/60
=50/60=5/6.
Let A worked with B for x number of days.
(A+B)'S x days work=5x/6
Remaining work=1-5x/6=(6-5x)/6
B can do 1/30 part of the work in 1 days
B can do whole part of the work in 30 days
B can do (6-5x)/6part of the work in 30×(6-5x)/6 days=5(6-5x)days
Given that B has completed the remaining in 10 days.
∴ 10=5(6-5x)
⇒10/5=6-5x
⇒2-6= -5x
⇒-4=-5x
⇒x=5/4
∴A left after 5/4 days.