A can do a piece of work in 20 days, B in 30 days and C in 40 days . They start working together. A works for 2 days and leaves B leaves 4 days before the work finishes. How long does the work last
Answers
Answered by
0
Answer:
Answer is 18 days
Step-by-step explanation:
Let the work get done in x days
Total amount of work done by A, B, & C =
6/20 + (x-6) /30 + x/60 = 1
18 + 2x-12 + x = 60
3x = 54
x = 18 days ANSWER