A can do a piece of work in 20 days whereas B can do it in 30 days both of them start the work together and work for sometime then B leaves if a completes the remaining work in 10 days then find the number of days for which they work together
Answers
Given :-
- A can do a piece of work in 20 days.
- B can do it in 30 days.
- Both Started Together.
- B left.
- A completes the remaining work in 10 days.
To Find :-
- The number of days for which they work together ?
Solution :- (By LCM Method).
LCM of 20 & 30 = 60unit = Let Total work.
So,
→ A alone can complete Total work in = 20 days .
→ Efficiency of A = (Total work) / No. of days = 60/20 = 3 unit/ day.
Similarly,
→ B alone can complete Total work in = 30 days .
→ Efficiency of A = (Total work) / No. of days = 60/30 = 2 unit/ day.
__________________
Now, it is given that, in last 10 days A alone did the work.
So,
→ in Last 10 days A did = 10 * 3 = 30 unit of work.
__________________
So, we can say That, rest work was done by Both of them , when they were together ,
Therefore,
→ left work = 60 - 30 = 30 unit.
→ Efficiency of A + B = 3 + 2 = 5 unit / day.
→ Time taken By them = (30/5) = 6 days. (Ans.)
Hence, A & B work together for 6 days.
__________________________________
- A can do a piece of work in 20 days whereas B can do it in 30 days both of them start the work together and work for sometime then B leaves if a completes the remaining work in 10 days
__________________________________
- The number of days for which they work together
__________________________________
As we know, the LCM of 30 & 20 is 60, Let 60 be the unit of work done
__________________________________
➠A can do the Total work in = 20 days
➠Efficiency of A = (Total work) / No. of days = 60/20 = 3 unit/ day
_________________________________
➠B can do The Total work in = 30 days
➠ Efficiency of A = (Total work) / No. of days = 60/30 = 2 unit/ day
__________________________________
Now, we know that A did work alone for 10 days...
So,
In last 10 days ,A did 30 units of work
__________________________________
We know than the rest of the work was done by both of 'em
Then,
The remaining work = (60-30) = 30 units of work
__________________________________
➠Efficiency of A + B = 3 + 2 = 5 unit/day
➠Work done by them = 30÷5 = 6 Days