A can do a piece of work in 24 days, B in 32 days and C in 64 days. All begin
to do it together but A leaves after 6 days and B leaves 6 days before the completion
of the work. The total number of days they worked for is :
(a) 20 days (b) 8days (c) 16 days (d) 24 days
(SSC, CGL, 20.7.2014)
Answers
Answered by
1
Answer:20
Step-by-step explanation:
Lets assume amt of work =1
Work done by A in 1 day = 1/24
Work done by B in 1 day = 1/32
Work done by C in 1 day = 1/64
Let consider the amt of days they worked as x
So =>
6A+(x-6)B+xC=1
6/24+(x-6)/32+x/64=1
(x-6)/32+x/64=1-6/24
(x-6)/32+x/64=1-1/4
(x-6)/32+x/64=3/4
2*(x-6)/64+x/64=3/4
(2x-12)/64+x/64=3/4
(3x-12)/64=3/4
(3x-12)=3/4×64
(3x-12)=3×16
3x=3×16+12
3x=48+12
3x=60
x=60/3
x=20
Similar questions