A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is:
Answers
Answered by
1
Answer: 15 days
Step-by-step explanation:
A does work in 24 days
so A's one day work = 1/24
B is 60% more efficient than A
B's one day work= 1/24 + (60/100 × 1/24)
⇒1/24 ( 1 + 60/100)
⇒160/2400
⇒1/15
thus B takes 15 days to complete the same work.
Answered by
6
Question
A can do a piece of work in 24 days. B is 60% more efficient than A. The number of days B take to do the same piece of work is
Answer:
Solution
Let the work done by A be x so,
x = 24 days
As per the question , 60% of x = b
= B's work
Now
If x = 24 days then,
Therefore, B can do the work in 14.4 days (or) 15days.
Hope it helps uh!!
Mark as Brainliest
Do follow and thank
Similar questions