Math, asked by Jessej7243, 9 months ago

A can do a piece of work in 28 days, while b can do the same piece of work in 42 days. They begin working together and 6 days before completion of work, a leaves. Find the total number of days taken to complete the

Answers

Answered by Anonymous
0

Answer:

piece of work done by a in one day-1by 28

piece of work done by b in one day-1by 42

a+b working together- 1/28 + 1/42

5/74 days

time taken to do the work- 1÷5/74

74/5=14 whole 4 by 5 days

i hope this is right.

Similar questions