A can do a piece of work in 40 days and B in 45 days. they work together for 10 days and then B goes away .In how many days will A finish the remaing work.
Answers
Answer:
Step-by-step explanation:
A —40
B—45
Here LCM is total work
Hence Lcm (40,45)= (8x5, 9x5)=8x9x5=360
A’s one day work is 360/40=9 unit
B’s one day work is 360/45=8 unit
in 10 days A does 90 unit and B does 80 units
total work completed is 90+80=170
remaining work is 360–170=190units
A’s one day work 9 unit
so for 190 units he need 190/9 days or 21 and 1/2 days
Answer:
190/9 days
Step-by-step explanation:
A takes 40 days to complete the work
=> Fraction of work done by A in one day = 1/40
B takes 45 days to complete the work
=> Fraction of work done by B in one day = 1/45
If they work together for 1 day, they will complete (1/40 + 1/45) of the work
Fraction of work completed by (A+B) in 1 day = 1/40 + 1/45
= 9/360 + 8/360
= 17/360
Fraction of work completed by (A+B) in 10 days = 10*(17/360) = 170/360
Fraction of work left incomplete = 1 - 170/360 = 190/360
Now,
B goes away and A is left alone.
A needs to complete 190/360 of the work
We know that A completes 1/40 of the work in 1 day
We have to find "x" so that A completes (190/360) of the work in x days
Using ratio and proportion, we get:
x = (190/360) ÷ (1/40)
= (190/360)*40
= 190/9
The number of days that A will take to complete the work (after B has left) is 190/9 or