A can do a piece of work in 60 days.he works for 15 days and then b alone finishes the remaining work in 30 days. the two together can finish the work in
Answers
Answered by
13
They toghether will take 24days to complete the work
Attachments:
Answered by
7
Together they can finish the work in 24 days.
Given data :
A finishes in = 60 days
A Works for = 15 days
B finishes remaining work in = 30 days
Let,the total amount of work = 1
So, A finishes in 60 days = 1
A finishes in 1 day = 1/60
A finishes in 15 days = 15/60 = 1/4
Remaining work = 1-1/4 = 3/4
B finishes in 30 days = 3/4
B finishes in 1 day = 1/40
So,in 1 day
A+B finishes = 1/60 + 1/40 = (2+3)/120 = 5/120 = 1/24
So they finishes 1/24 work in = 1 day
They finishes 1 work in = 1 × 24/1 = 24 days (answer)