Math, asked by abdulmabood8741, 1 year ago

A can do a piece of work in 60days working 14 hours. B has the same efficiency as of

a. A and b started working together. A works 5,6,7 and 8 hours respectively on first four days and repeats the cycle again. Then b has to work how many hours daily if they together completed the work in 80 days?

Answers

Answered by amitnrw
24

Answer:

B has to work 4 hrs daily

Step-by-step explanation:

Number of rs required by A to complete work = 60 * 14 = 840 hrs

Work done by A in 1 hr = 1/840

B has same efficiency

=> Work done by B in 1 hr = 1/840

Work done by A in 4 days = (1/840)(5 + 6 + 7 + 8) = 26/840 = 13/420

Work done by A in 80 Days = (80/4)  * (13/420) = 13/21

Work to be done by B  = 1 - 13/21  = 8/21

Work done by B in 80 days = 8/21

Work done by B in 1 days = (8/21)/80 = 1/210

Work done by B in 1 hr = 1/840

Work done by B in x Hrs  = x/840

=> x/840 = 1/210

=> x =  4

B has to work 4 hrs daily