Math, asked by Sankalpparab2127, 1 year ago

A can do a piece of work in 80 days. A works for 10 days, then b complete the remaining work in 42 days. In how many days will (a +

b.Do this work together

Answers

Answered by GauravSaxena01
0

Answer:

A can do work in 1 day = 1/80

A can do work in 10 days  = 10/80 =1/8

Remaining work=1-1/8  = 7/8

B can  complete remaining work in 42 days  =7/8 part of work

B can complete in 1 day work = 1/ 48 part of work

So,

B alone can complete it in 48 days

Work done by both in 1 day

=1/80+1/48

=(3+5)/240

=1/30

So they can finish the work together in 30days

==============

@GauravSaxena01