Math, asked by abhinandansarkar48, 6 months ago

A can do a piece of work in 80 days and B in 100 days. They work together for 20 days and then B goes away. In how many days will A finish the remaining work?​

Answers

Answered by amreshkumar1080
0

Answer:

80 days

Step-by-step explanation:

Similar questions