*A* can do a piece of work in 9 days while *B* can do it in 6 days and with the help of *C* they finish the work in 3 days . In how many days *C* can finish the work alone ?
Answers
Answered by
1
Step-by-step explanation:
C can do alone work in 18 days
Answered by
1
Answer:
18...................