A can do a work in 10 days and B can do the same work in 15 days . They started doing the work together .A left 2 days before the work was finished. What time was taken to finish?
Answers
Answered by
0
Step-by-step explanation:
Let us take time taken for work to finish as x
A's one day work=1/10
B's one day work=1/15
A's 2 day work + B's x day work = 1
2×1/10+x×1/15=1
1/5+x/15=1
3+x/15=1
3x/15=1
3x=1×15
=15
x=15/3=5
Time taken to finish the work = 5