a can do a work in 10 days, b can do a work in 18 days a b c can finish the work in 4 days . in what time will c be able to complete the work

Answers

Answered by ItzVenomKingXx
1

A can do a piece of work in = 10 days

B can do a piece of work in = 18 days

(A + B + C) can do a piece of work in = 4 days

∴ A’s 1 day work = 1/10

B’s 1 day work = 1/18

(A + B)’s 1 day work = 1/10 + 1/18 = (9 +5)/90

= 14/90 = 7/45

(A + B + C)’s 1 day work = ¼

∴ C’s 1 day work =1/4 – 7/45

= (45 – 28)/180 = 17/180

∴ C can do the piece of work in = 180/17 days

= 10. 10/17 days

This is the answer