A can do a work in 12 days and B alone can fo it in 16 days they worked on it for 3 days and A left .how long did B take to finish the remaining work
Answers
Correct Question:
A can do work in 12 days and B alone can do it in 16 days. If they worked on it for 3 days and then A left. How long did B take to finish the remaining work?
Given:
Two people:-
- A and B
Who can do work for:-
- A = 12 days
- B = 16 days
If they worked for:-
- Both A and B = 3 days
Then A left the work and B did the remaining work.
What To Find:
We have to how long i.e the number of days B takes to finish the remaining work.
How To Find:
To find the number of days, we have to find:-
- Find how much work can A do in 1 day.
- Find how much work can B do in 1 day.
- Add A's and B's work of 1 day.
- Find A's and B's work for 3 days.
- Find the number of days B took to complete the whole work.
Solution:
• For A:-
• For B:-
• Find the sum for 1 day:-
Take the LCM of 12 and 16 i.e 48,
Multiply the numerator and the denominator,
Add the fractions,
• Find the sum of 3 days works:-
Number of works in 1 day by both A and B,
Number of works in 3 days by both A and B,
Cancel 48 and 3 and it will become 16,
• Find the number of days B took to complete the whole work:-
Find the remaining work,
Take the LCM of 1 and 16 i.e 16,
Multiply the numerators and denominators,
Subtract the fractions,
We know that,
We also know that,
So,
Cancel 16 and 16,
Correct Question:
A can do work in 12 days and B alone can do it in 16 days. If they worked on it for 3 days and then A left. How long did B take to finish the remaining work?
Given:
Two people:-
A and B
Who can do work for:-
A = 12 days
B = 16 days
If they worked for:-
Both A and B = 3 days
Then A left the work and B did the remaining work.
What To Find:
We have to how long i.e the number of days B takes to finish the remaining work.
How To Find:
To find the number of days, we have to find:-
Find how much work can A do in 1 day.
Find how much work can B do in 1 day.
Add A's and B's work of 1 day.
Find A's and B's work for 3 days.
Find the number of days B took to complete the whole work.
Solution:
• For A:-
• For B:-
• Find the sum for 1 day:-
Take the LCM of 12 and 16 i.e 48,
Multiply the numerator and the denominator,
Add the fractions,
• Find the sum of 3 days works:-
Number of works in 1 day by both A and B,
Number of works in 3 days by both A and B,
Cancel 48 and 3 and it will become 16,
• Find the number of days B took to complete the whole work:-
Find the remaining work,
Take the LCM of 1 and 16 i.e 16,
Multiply the numerators and denominators,
Subtract the fractions,
We know that,
We also know that,
So,
Cancel 16 and 16,