A can do a work in 12 days while b can do it in 15 days. they undertake to complete it together for rs. 450. what will be the share of a in this amount of money
Answers
Answered by
4
A:B =5:4
5x+4x=450
x=50
A's share = 250 Rs.
B's share= 200 Rs
5x+4x=450
x=50
A's share = 250 Rs.
B's share= 200 Rs
Answered by
1
Answer:
Share of A's is Rs.250.
Step-by-step explanation:
Given : A can do a work in 12 days while b can do it in 15 days. They undertake to complete it together for Rs. 450.
To find : What will be the share of a in this amount of money?
Solution :
A can do a work in 12 days.
Work done by A is 1 day =
B can do a work in 15 days.
Work done by B is 1 day =
The ratio of their wages is
So, Share of A is
Share of B is 450-250=Rs.200
Therefore, Share of A's is Rs.250.