Math, asked by ChamanGhotiya, 1 year ago

A can do a work in 15 days and B can do it in 10 days. B works at it for 5 days and leaves. A alone can finish the remaining work in ______.

A. 6.5 days

B. 7.5 days

C. 8 days

D. 8.5 days.

SHOW WITH PROPER WORKING!

Answers

Answered by ShAiLeNdRaKsP
1
Hey friend.....☺

HERE IS YOUR ANSWER

A can do work in 15 days
B can do it in 10 days

B works 5 days and leaves it

In this way B has done 1/2 of the work

(10 days= full work and 5days = half of the work)

Now A has to do only half of the work

(Again A does full work in 15 days that is taking 1 as complete work)

Now , multiply 15 × 1/2
=15/2
= 7.5 days is the answer

Hope it helps you

Thanks :-)